Scheduling and line balancing
A scheduling rule optimises a specific objective under specific assumptions. “Best sequence” is incomplete without the objective, release dates and machine arrangement. Draw a time table when calculating makespan; the second machine may wait for both a job and its own availability.
4.1 Job measures and dispatching priorities
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
| Rule | Sort order | Guaranteed result under the stated basic model |
|---|---|---|
| FCFS | Arrival order | Simple/fair arrival discipline; no general optimality claim |
| SPT | Increasing processing time | Minimum total/mean completion and flow time |
| Weighted SPT | Increasing , | Minimum |
| EDD | Increasing due date | Minimum maximum lateness, hence maximum tardiness |
| Critical ratio | Increasing CR | Dynamic urgency heuristic |
| Least slack | Increasing slack | Urgency heuristic |
The optimality statements assume one machine, all jobs available at time zero, no pre-emption, and fixed processing times with no sequence-dependent setups. EDD does not generally minimise total tardiness or the number of late jobs. For minimum number of late jobs in this basic model: scan EDD order; whenever the accumulated duration exceeds the current due date, remove the longest job from the retained set. Append removed jobs after retained jobs (Moore–Hodgson rule).
4.2 Two-machine flow shop
Past papers · ME 2020–2026 (10 papers): 2 questions, 3 marks
Johnson's rule minimises makespan for jobs processed first on machine 1 then machine 2, when all are initially available, processing is non-preemptive, each machine handles one job at a time, and waiting between machines is allowed. Processing times are fixed; setups must be negligible or included without sequence dependence.
Select the smallest processing time among all unscheduled jobs on either machine. If it is on machine 1, place that job in the earliest vacant position; if on machine 2, place it in the latest vacant position. Remove it and repeat. Ties may produce several optimal sequences; calculate makespan to compare offered choices.
Original three-job schedule; blank time on a machine is idle time.
4.3 No-wait processing
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
“No waiting between operations” adds a constraint absent from ordinary Johnson scheduling. It may require delaying a job's start on machine 1; applying Johnson blindly is unsafe.
4.4 Assembly-line balancing
Assign indivisible tasks to stations subject to precedence and a cycle-time limit. The target cycle time comes from demand; the achievable cycle time of a fixed assignment is its longest station workload. A lower bound on station count need not be feasible.
Last-minute recall
- Lateness can be negative; tardiness cannot.
- CR uses due date minus current date.
- SPT minimises mean flow time in the basic single-machine model.
- EDD minimises maximum lateness, not total tardiness.
- Johnson requires waiting between machines to be allowed.
- The second machine starts at the later of job arrival and machine availability.
- Round the station-count bound up; then check precedence and indivisibility.