Aggregate production planning
An aggregate plan selects workforce, production and inventory across a medium-term horizon for product families. Disaggregate it into a master production schedule, check capacity, and revise it when demand or resource limits change.
3.1 Planning hierarchy and strategies
Routing selects operations and their path; loading assigns work to resources; scheduling sets times and sequence; dispatching releases work; follow-up compares actual progress with the plan and corrects delays.
| Strategy | Quantity held steady | Main tradeoff |
|---|---|---|
| Level | Workforce and/or production rate | Inventory or backlog absorbs changing demand |
| Chase | Production follows demand | Hiring, layoffs, hours or subcontracting vary |
| Mixed | Selected limits on both | Balance inventory, workforce and capacity costs |
Longer-range capacity decisions constrain the aggregate plan. The master production schedule specifies end items and periods; MRP determines components; detailed scheduling assigns shop operations. Aggregate units must use a common conversion basis, such as standard labour-hours, when products have different workloads.
3.2 Material and workforce balances
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
3.3 Comparing plan costs
Count only costs that differ between feasible plans, but include fixed or purchase costs when the question requests total cost. A profitable plan may have an objective if these are the only specified revenue/cost terms; is revenue per sold unit. Production consumes capacity whether or not the unit is sold immediately.
Last-minute recall
- Level production does not imply level demand.
- Opening stock plus receipts minus issues gives closing stock.
- Backlog is an obligation, not negative physical on-hand stock.
- Capacity sums over products separately for each resource and period.
- Workforce changes use hires minus layoffs.
- Use the stated inventory-cost convention and avoid counting wages twice.