Materials requirement planning
MRP converts the end-item schedule into dated requirements for dependent-demand components. Three inputs are essential: the master production schedule, the bill of materials (BOM), and inventory records including receipts, lead times and lot-sizing rules.
5.1 Product structure and explosion
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
A BOM states how many units of each child are needed per parent. Multiply usage quantities along a path and add requirements over all paths. Process a shared component only after all its parents' requirements have been accumulated; low-level coding places an item at its deepest occurrence for this purpose.
Original BOM with usage per parent marked on every connection.
5.2 Netting and lead-time offset
5.3 Lot sizing and capacity checks
Past papers · ME 2020–2026 (10 papers): 1 question, 1 mark
| Lot rule | How to apply | Tradeoff |
|---|---|---|
| Lot-for-lot (L4L) | Receive exactly each positive net requirement | Little avoidable inventory; many setups |
| Fixed order quantity | Order a prescribed quantity or its required multiple | May leave stock for later periods |
| EOQ-based lot | Use an economical fixed lot estimated from average demand | Average demand may hide lumpy requirements |
| Fixed period quantity | Cover a stated number of future periods | Variable quantities, periodic coverage |
| Period order quantity | Convert EOQ to a chosen coverage interval, then cover actual requirements | Round interval according to the stated rule |
| Part-period balancing | Group future requirements until holding cost is near one setup cost; compare neighbours | Heuristic tradeoff between holding and setup |
Basic MRP plans materials assuming stated lead times; it does not itself guarantee finite capacity. Capacity requirements planning checks work-centre loads. MRP II extends the system to manufacturing resources and financial coordination; ERP integrates wider enterprise functions. Keep those distinctions conceptual.
Last-minute recall
- MPS, BOM and inventory records are MRP inputs.
- Dependent demand comes from parent requirements, not a separate forecast.
- Add all paths to a shared component.
- Explode planned parent releases, not parent completion dates.
- Net available stock and scheduled receipts before lot sizing.
- Offset receipts backwards by lead time to obtain releases.
- Zero setup cost with positive holding cost favours L4L.