Chapter 5

Materials requirement planning

MRP converts the end-item schedule into dated requirements for dependent-demand components. Three inputs are essential: the master production schedule, the bill of materials (BOM), and inventory records including receipts, lead times and lot-sizing rules.

5.1 Product structure and explosion

Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks

A BOM states how many units of each child are needed per parent. Multiply usage quantities along a path and add requirements over all paths. Process a shared component only after all its parents' requirements have been accumulated; low-level coding places an item at its deepest occurrence for this purpose.

Original BOM with usage per parent marked on every connection.Original BOM with usage per parent marked on every connection.

5.2 Netting and lead-time offset

5.3 Lot sizing and capacity checks

Past papers · ME 2020–2026 (10 papers): 1 question, 1 mark

Lot ruleHow to applyTradeoff
Lot-for-lot (L4L)Receive exactly each positive net requirementLittle avoidable inventory; many setups
Fixed order quantityOrder a prescribed quantity or its required multipleMay leave stock for later periods
EOQ-based lotUse an economical fixed lot estimated from average demandAverage demand may hide lumpy requirements
Fixed period quantityCover a stated number of future periodsVariable quantities, periodic coverage
Period order quantityConvert EOQ to a chosen coverage interval, then cover actual requirementsRound interval according to the stated rule
Part-period balancingGroup future requirements until holding cost is near one setup cost; compare neighboursHeuristic tradeoff between holding and setup

Basic MRP plans materials assuming stated lead times; it does not itself guarantee finite capacity. Capacity requirements planning checks work-centre loads. MRP II extends the system to manufacturing resources and financial coordination; ERP integrates wider enterprise functions. Keep those distinctions conceptual.

Last-minute recall

  • MPS, BOM and inventory records are MRP inputs.
  • Dependent demand comes from parent requirements, not a separate forecast.
  • Add all paths to a shared component.
  • Explode planned parent releases, not parent completion dates.
  • Net available stock and scheduled receipts before lot sizing.
  • Offset receipts backwards by lead time to obtain releases.
  • Zero setup cost with positive holding cost favours L4L.