PERT and completion probability
PERT replaces a fixed activity duration with an estimate of its mean and variance. Calculate the network using mean durations, then use the stated probabilistic approximation. Distinguish a fixed path's duration from the maximum of several random path durations.
2.1 Three activity-time estimates
Let denote optimistic, most likely and pessimistic activity times, with . The most likely time is a mode, not automatically the mean.
2.2 Mean and variance of a path
Past papers · ME 2020–2026 (10 papers): 3 questions, 5 marks
A path contains activities in series. Its duration is their sum. Compute every candidate path's mean, or run the forward pass using .
Two paths that share a random activity are dependent even if all individual activity durations are independent. For independent activity durations, the covariance of two path durations equals the sum of the variances of their shared activities.
2.3 Deadline probabilities and uncertainty
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
For a fixed critical path with mean and standard deviation , the normal approximation converts a deadline into a dimensionless distance from the mean. It is exact for a sum of independent normal activity times, but only approximate for general PERT durations.
| 0 | 0.5000 | 1.282 | 0.9001 |
| 0.5 | 0.6915 | 1.645 | 0.9500 |
| 1.0 | 0.8413 | 1.960 | 0.9750 |
| 2.0 | 0.9772 | 2.326 | 0.9900 |
| 2.5 | 0.9938 | 3.0 | 0.9987 |
Use . The familiar 68.27%, 95.45% and 99.73% refer to the two-sided intervals within 1, 2 and 3 standard deviations, not the probabilities of meeting one upper deadline.
Last-minute recall
- Order the three estimates: optimistic, most likely, pessimistic.
- Use the mean estimate in the network pass.
- A variance carries squared time units.
- Sum independent variances; take one square root at the end.
- A mean-network duration is an approximation to expected project duration.
- At a normal path's mean, completion probability is one half.
- A one-sided 95% deadline uses about 1.645 standard deviations.
- Shared activities correlate path durations.