Project networks and CPM
Project logic determines which activities can overlap and which must wait. First draw a faithful network, then calculate earliest and latest times. Unless stated otherwise, activities are non-preemptive, resources are sufficient, and every precedence link is finish-to-start with zero lag.
1.1 AOA, AON and network logic
Past papers · CE 2020–2026 (14 papers): 1 question, 2 marks
An activity is a task with a duration. An event is an instantaneous milestone. A predecessor must meet its stated relationship before the successor can proceed.
| Feature | Activity on arrow (AOA) | Activity on node (AON) |
|---|---|---|
| Task | Directed arrow between events | Node containing the task and duration |
| Link meaning | Activity, or a dummy | Precedence constraint |
| Dummy | Dashed arrow, zero duration and zero resources | Usually unnecessary for precedence logic |
| Joining branches | Event waits for every incoming activity | Activity waits for every required predecessor |
| Time labels | Earliest/latest event times | Earliest/latest activity starts and finishes |
Use one start and one finish, introducing zero-duration boundary milestones when needed. Include all terminal tasks in the project finish. A project precedence network has no directed cycle. Every activity must be reachable from the start and lead to the finish. Number AOA events in topological order: repeatedly number an event whose predecessors have all been numbered; every arrow then goes from a smaller to a larger event number. Numbers need not be consecutive along a path.
In standard AOA notation two distinct activities must not use the same ordered event pair. A dummy can distinguish them or enforce a dependency without falsely imposing another one. Example: A and B start together; C follows A alone, while D follows both A and B. Separate A's and B's finish events and add a dummy from A's finish to B's finish before D. Do not merge the two finish events: that would make C wait for B.
The same precedence logic in AON and AOA; the dashed AOA link is a zero-duration dummy.
1.2 Forward and backward passes in AOA
For activity , let be duration and let be earliest and latest event occurrence times. Start the time origin at zero. denotes earliest project completion; denotes the finish deadline chosen for the backward pass.
A negative slack under an imposed early deadline indicates that the present durations cannot meet it. It does not tell you which resource must be added. A late imposed deadline can give positive slack even on a longest path.
1.3 Activity times in AON
Past papers · CE 2020–2026 (14 papers): 3 questions, 6 marks · ME 2020–2026 (10 papers): 1 question, 2 marks
For activity , is duration; are earliest start/finish and latest start/finish. Let and be its immediate predecessors and successors.
1.4 Total, free, independent and interfering float
Past papers · CE 2020–2026 (14 papers): 3 questions, 6 marks · ME 2020–2026 (10 papers): 2 questions, 3 marks
Float is available scheduling freedom, not permission to delay every activity by its full float simultaneously. Activities on a common path share time margins. For AOA, is the tail event and the head event of the activity.
| Margin | What remains protected |
|---|---|
| Total float | Project finish at the specified deadline |
| Free float | Earliest occurrence of the head event; earliest starts of immediate successors |
| Independent float | Earliest head event even if the tail occurs at its latest time |
| Interfering float | Part of total float that can shift successor early times without shifting project finish |
An activity is critical in ordinary CPM if its total float is zero. In AOA this requires both endpoint events to be critical and ; zero event slacks alone are insufficient. A critical path is a start-to-finish path whose duration equals . There can be several.
1.5 Precedence links with lags
A lag is a specified minimum separation; a negative lag is a lead. AON allows relationships other than finish-to-start. Use them only when a question explicitly specifies them.
Last-minute recall
- AOA nodes are events; AON nodes are activities.
- A dummy enforces logic and consumes neither time nor resources.
- Forward pass: maximum; backward pass: minimum.
- Include every terminal activity in the finish milestone.
- Longest path gives the earliest possible project duration.
- Zero slack at both events does not alone make their connecting activity critical.
- Float on a path is shared, not additive.
- Specify the deadline before interpreting negative float.