Project logic determines which activities can overlap and which must wait. First draw a faithful network, then calculate earliest and latest times. Unless stated otherwise, activities are non-preemptive, resources are sufficient, and every precedence link is finish-to-start with zero lag.

1.1 AOA, AON and network logic

Past papers · CE 2020–2026 (14 papers): 1 question, 2 marks

An activity is a task with a duration. An event is an instantaneous milestone. A predecessor must meet its stated relationship before the successor can proceed.

FeatureActivity on arrow (AOA)Activity on node (AON)
TaskDirected arrow between eventsNode containing the task and duration
Link meaningActivity, or a dummyPrecedence constraint
DummyDashed arrow, zero duration and zero resourcesUsually unnecessary for precedence logic
Joining branchesEvent waits for every incoming activityActivity waits for every required predecessor
Time labelsEarliest/latest event timesEarliest/latest activity starts and finishes

Use one start and one finish, introducing zero-duration boundary milestones when needed. Include all terminal tasks in the project finish. A project precedence network has no directed cycle. Every activity must be reachable from the start and lead to the finish. Number AOA events in topological order: repeatedly number an event whose predecessors have all been numbered; every arrow then goes from a smaller to a larger event number. Numbers need not be consecutive along a path.

In standard AOA notation two distinct activities must not use the same ordered event pair. A dummy can distinguish them or enforce a dependency without falsely imposing another one. Example: A and B start together; C follows A alone, while D follows both A and B. Separate A's and B's finish events and add a dummy from A's finish to B's finish before D. Do not merge the two finish events: that would make C wait for B.

The same precedence logic in AON and AOA; the dashed AOA link is a zero-duration dummy.The same precedence logic in AON and AOA; the dashed AOA link is a zero-duration dummy.

1.2 Forward and backward passes in AOA

For activity i→ji\to j, let tijt_{ij} be duration and let Ei,LiE_i,L_i be earliest and latest event occurrence times. Start the time origin at zero. TprojT_{\rm proj} denotes earliest project completion; TdT_d denotes the finish deadline chosen for the backward pass.

A negative slack under an imposed early deadline indicates that the present durations cannot meet it. It does not tell you which resource must be added. A late imposed deadline can give positive slack even on a longest path.

1.3 Activity times in AON

Past papers · CE 2020–2026 (14 papers): 3 questions, 6 marks · ME 2020–2026 (10 papers): 1 question, 2 marks

For activity aa, tat_a is duration; ESa,EFa,LSa,LFaES_a,EF_a,LS_a,LF_a are earliest start/finish and latest start/finish. Let P(a){\cal P}(a) and S(a){\cal S}(a) be its immediate predecessors and successors.

1.4 Total, free, independent and interfering float

Past papers · CE 2020–2026 (14 papers): 3 questions, 6 marks · ME 2020–2026 (10 papers): 2 questions, 3 marks

Float is available scheduling freedom, not permission to delay every activity by its full float simultaneously. Activities on a common path share time margins. For AOA, ii is the tail event and jj the head event of the activity.

MarginWhat remains protected
Total floatProject finish at the specified deadline
Free floatEarliest occurrence of the head event; earliest starts of immediate successors
Independent floatEarliest head event even if the tail occurs at its latest time
Interfering floatPart of total float that can shift successor early times without shifting project finish

An activity is critical in ordinary CPM if its total float is zero. In AOA this requires both endpoint events to be critical and Ej−Ei=tijE_j-E_i=t_{ij}; zero event slacks alone are insufficient. A critical path is a start-to-finish path whose duration equals TprojT_{\rm proj}. There can be several.

1.5 Precedence links with lags

A lag is a specified minimum separation; a negative lag is a lead. AON allows relationships other than finish-to-start. Use them only when a question explicitly specifies them.

Last-minute recall

  • AOA nodes are events; AON nodes are activities.
  • A dummy enforces logic and consumes neither time nor resources.
  • Forward pass: maximum; backward pass: minimum.
  • Include every terminal activity in the finish milestone.
  • Longest path gives the earliest possible project duration.
  • Zero slack at both events does not alone make their connecting activity critical.
  • Float on a path is shared, not additive.
  • Specify the deadline before interpreting negative float.