Project crashing and cost–time trade-offs
Crashing spends additional direct cost to shorten selected activities. It reduces project duration only when every currently controlling path is shortened. Recalculate the network whenever an activity reaches its crash limit or another path becomes critical.
3.1 Activity cost slope and crash limits
Past papers · ME 2020–2026 (10 papers): 1 question, 1 mark
Normal duration and crash duration bound activity ; corresponding direct costs are and . The standard exam model interpolates linearly between these two points.
3.2 Choosing the economical project duration
Past papers · CE 2020–2026 (14 papers): 1 question, 2 marks
Start with all normal times. With one critical path, choose the cheapest available reduction on that path, subject to crash limits and the gap to the next-longest path. With several critical paths, choose a feasible set of reductions that shortens all of them at the least total cost. A common activity may do this more cheaply than separate activities.
Last-minute recall
- Cost slope uses normal time minus crash time in the denominator.
- The slope has currency/time units and is normally nonnegative.
- Check the reduction potential before ranking candidates.
- Shorten every active critical path to shorten the project.
- Recompute paths after each effective change.
- Compare marginal direct cost with actual project-level savings.