Chapter 5

Hydrographs and catchment response

A storm hydrograph includes direct runoff and baseflow. Remove the latter before constructing a unit hydrograph, and restore it only after computing the direct response to a new storm.

5.1 Hydrograph components and volume

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

The rising limb reflects arrival and increasing catchment storage; the crest contains the peak; recession reflects drainage of storage. Time to peak is measured from the specified storm origin. Basin lag commonly runs from the excess-rainfall centroid to the direct-runoff peak; state the definition used.

Common separation methods are a horizontal baseflow line, a straight line to an assumed recession endpoint, and a smooth extension of groundwater recession. They are approximations; use the separation stated in the question. Do not assume a universal number of days between peak and endpoint.

A direct response is the part above the chosen baseflow line; the full curve is total streamflow.A direct response is the part above the chosen baseflow line; the full curve is total streamflow.

5.2 Unit hydrograph definition and scaling

Past papers · CE 2020–2026 (14 papers): 2 questions, 3 marks

A DD-hour unit hydrograph (UH) is the direct-runoff response to 1 cm of excess rainfall spread uniformly over the catchment at constant intensity during DD hours. Assume linearity, superposition and a time-invariant catchment. Duration means duration of excess rainfall, not the hydrograph time base or the sampling interval.

5.3 Multiple pulses and inverse calculation

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

Apply each excess-rainfall pulse to the same-duration UH, delay it by its start time, and add the responses. First make the rainfall intervals agree with the UH duration.

5.4 Changing unit duration

Past papers · CE 2020–2026 (14 papers): 3 questions, 5 marks

Adding delayed unit hydrographs adds runoff depths too. Normalise the sum back to one unit depth. The S-curve extends this idea to any target duration for which the curves can be evaluated consistently.

To recover a shorter UH from a longer one, solve the same averaging relation recursively, or use the S-curve. For example, U2D(t)=[UD(t)+UD(t−D)]/2U_{2D}(t)=[U_D(t)+U_D(t-D)]/2 gives UD(t)=2U2D(t)−UD(t−D)U_D(t)=2U_{2D}(t)-U_D(t-D) with zero ordinates before the origin. Shortening is sensitive to inconsistent data; do not simply compress the time axis.

5.5 Synthetic and instantaneous response

Synthetic methods estimate an ungauged basin response from geometry and regional coefficients. Preserve unit volume after choosing the curve shape; agreement of only peak and lag is insufficient.

Last-minute recall

  • Separate baseflow before unit normalisation.
  • UH duration and ordinate interval need not be the same.
  • One centimetre over one square kilometre is 10,000 m3^3.
  • Superpose direct responses; add baseflow once.
  • Longer-duration UH construction requires division by the number of summed units.
  • S-curve plateau is basin volume per unit storm duration.
  • Synthetic coefficients depend on region and units.
  • An instantaneous response is normalised differently from a 1-cm discharge hydrograph.