Project types, estimation and rates
An estimate translates drawings and specifications into measured work and cost. Keep scope, units, quantities, rates and percentage bases visible so that each step can be audited.
6.1 Project and organisation types
Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark
| Project family | Typical work | Characteristic planning concern |
|---|---|---|
| Residential | Houses, apartments | Repeated units, services and finishes |
| Institutional/commercial | Hospitals, schools, offices | Functional requirements and service coordination |
| Industrial | Plants, process facilities | Civil–mechanical–electrical interfaces and commissioning |
| Infrastructure/heavy civil | Roads, bridges, dams, tunnels, water systems | Site variability, access, environmental and public interfaces |
| Maintenance/rehabilitation | Repair or upgrading of existing assets | Existing condition and continuity of service |
Project type describes the facility/work; public/private describes ownership; lump-sum/item-rate describes payment. These classifications are independent.
| Organisation | Authority and staffing | Trade-off |
|---|---|---|
| Functional | Specialists remain under department heads | Strong specialist support; project coordination crosses departments |
| Pure project/projectised | Dedicated team and strong project-manager authority | Fast project decisions; possible duplication and reassignment issues |
| Matrix | Shared functional and project responsibilities | Flexible specialist sharing and responsiveness; dual authority can create conflict |
6.2 Estimate purpose and measurement
Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark
A preliminary estimate supports feasibility and budgeting using available scope, floor area, capacity or analogous projects. It may be refined as planning and design develop. A detailed estimate uses measured item quantities and item rates; it supports tendering and execution cost control. A revised estimate responds to a changed expected total; a supplementary estimate identifies additional work not included in the original scope.
| Work | Common measurement unit | Do not confuse with |
|---|---|---|
| Excavation, concrete, masonry | m³ | A plan area without depth |
| Plaster, painting, flooring, formwork contact | m² | Concrete volume or volume of shutter material |
| Reinforcement/structural steel | kg or tonne | Nominal bar length alone |
| Pipes and similar linear items | m | Accessories separately measured as specified |
| Fixtures | number | A universal percentage allowance |
BOQ means bill of quantities. Read the specification to decide whether labour, material, plant, transport, testing and temporary works are included in an item rate. Code/contract deduction conventions can differ from simple geometric net area; apply a supplied convention and do not invent a deduction threshold.
6.3 Long-wall and short-wall quantities
At each footing or wall level, identify the centre-to-centre dimensions and that layer's breadth. Long walls are measured out-to-out; cross walls are measured in-to-in to avoid overlapping corners.
6.4 Centre-line method and junctions
The centre-line method is quick when wall sections are uniform and symmetric about the same centre lines. At an isolated rectangular enclosure with constant layer width, the perimeter method accounts for the corner geometry exactly. Internal branches need junction corrections.
A centre-line enclosure with an internal branch; its two ends each lose half the through-wall breadth.
6.5 Rate analysis and price bases
Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark
A unit rate combines delivered material quantities, labour effort, equipment time and applicable overhead/profit. Material wastage belongs to the specified quantity basis; transport includes the specified lead and lift. Fixed overhead and output-dependent costs behave differently when production changes.
For a mix stated in dry-volume ratios, multiply each constituent's ratio share by the specified total dry volume; convert to mass using the appropriate supplied bulk density. Do not assume a universal dry-volume multiplier for every concrete or mortar. Equipment and labour productivity determine hours per unit; reducing output with unchanged hourly cost raises the unit rate.
Last-minute recall
- Facility type, organisation form and payment contract are separate classifications.
- Preliminary estimates support budgeting; detailed estimates support measured cost control.
- Match quantity units to rate units before adding costs.
- Long-wall length adds the layer width; short-wall length subtracts it.
- Recalculate for each footing width.
- Centre-line junction corrections depend on what has already been counted.
- Formwork is usually measured by contact area; reinforcement by mass.
- A percentage of bid price is not the same as a percentage of cost.