Chapter 6

Project types, estimation and rates

An estimate translates drawings and specifications into measured work and cost. Keep scope, units, quantities, rates and percentage bases visible so that each step can be audited.

6.1 Project and organisation types

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

Project familyTypical workCharacteristic planning concern
ResidentialHouses, apartmentsRepeated units, services and finishes
Institutional/commercialHospitals, schools, officesFunctional requirements and service coordination
IndustrialPlants, process facilitiesCivil–mechanical–electrical interfaces and commissioning
Infrastructure/heavy civilRoads, bridges, dams, tunnels, water systemsSite variability, access, environmental and public interfaces
Maintenance/rehabilitationRepair or upgrading of existing assetsExisting condition and continuity of service

Project type describes the facility/work; public/private describes ownership; lump-sum/item-rate describes payment. These classifications are independent.

OrganisationAuthority and staffingTrade-off
FunctionalSpecialists remain under department headsStrong specialist support; project coordination crosses departments
Pure project/projectisedDedicated team and strong project-manager authorityFast project decisions; possible duplication and reassignment issues
MatrixShared functional and project responsibilitiesFlexible specialist sharing and responsiveness; dual authority can create conflict

6.2 Estimate purpose and measurement

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

A preliminary estimate supports feasibility and budgeting using available scope, floor area, capacity or analogous projects. It may be refined as planning and design develop. A detailed estimate uses measured item quantities and item rates; it supports tendering and execution cost control. A revised estimate responds to a changed expected total; a supplementary estimate identifies additional work not included in the original scope.

WorkCommon measurement unitDo not confuse with
Excavation, concrete, masonrym³A plan area without depth
Plaster, painting, flooring, formwork contactm²Concrete volume or volume of shutter material
Reinforcement/structural steelkg or tonneNominal bar length alone
Pipes and similar linear itemsmAccessories separately measured as specified
FixturesnumberA universal percentage allowance

BOQ means bill of quantities. Read the specification to decide whether labour, material, plant, transport, testing and temporary works are included in an item rate. Code/contract deduction conventions can differ from simple geometric net area; apply a supplied convention and do not invent a deduction threshold.

6.3 Long-wall and short-wall quantities

At each footing or wall level, identify the centre-to-centre dimensions and that layer's breadth. Long walls are measured out-to-out; cross walls are measured in-to-in to avoid overlapping corners.

6.4 Centre-line method and junctions

The centre-line method is quick when wall sections are uniform and symmetric about the same centre lines. At an isolated rectangular enclosure with constant layer width, the perimeter method accounts for the corner geometry exactly. Internal branches need junction corrections.

A centre-line enclosure with an internal branch; its two ends each lose half the through-wall breadth.A centre-line enclosure with an internal branch; its two ends each lose half the through-wall breadth.

6.5 Rate analysis and price bases

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

A unit rate combines delivered material quantities, labour effort, equipment time and applicable overhead/profit. Material wastage belongs to the specified quantity basis; transport includes the specified lead and lift. Fixed overhead and output-dependent costs behave differently when production changes.

For a mix stated in dry-volume ratios, multiply each constituent's ratio share by the specified total dry volume; convert to mass using the appropriate supplied bulk density. Do not assume a universal dry-volume multiplier for every concrete or mortar. Equipment and labour productivity determine hours per unit; reducing output with unchanged hourly cost raises the unit rate.

Last-minute recall

  • Facility type, organisation form and payment contract are separate classifications.
  • Preliminary estimates support budgeting; detailed estimates support measured cost control.
  • Match quantity units to rate units before adding costs.
  • Long-wall length adds the layer width; short-wall length subtracts it.
  • Recalculate for each footing width.
  • Centre-line junction corrections depend on what has already been counted.
  • Formwork is usually measured by contact area; reinforcement by mass.
  • A percentage of bid price is not the same as a percentage of cost.