Chapter 7

Project updating and monitoring

Measure physical progress and cost at the same status date. Updating forecasts the remaining work; monitoring compares that forecast and actual performance with the approved baseline.

7.1 Status date and remaining work

Record actual starts/finishes, quantities completed, actual expenditure and revised remaining durations. Completed work is historical; unfinished work is scheduled from the status date, respecting outstanding predecessors and constraints. Recompute the forecast completion and identify newly critical work. A delayed formerly noncritical activity may become critical. Approve scope/baseline changes separately rather than erasing a variance by silently resetting the baseline.

AOA/AON construction, forward/backward passes, floats, PERT and crashing: see the Operations Research handbook.

A bar chart compares planned and actual activity dates; a milestone chart records key completion events. A cumulative S-curve plots planned/earned work or cost against time; it need not be exactly S-shaped. Spending less than planned can indicate delayed work rather than a saving. A resource histogram exposes periods of excessive demand. Smoothing uses available float without extending the required finish; levelling respects resource limits and may delay completion.

7.2 Earned value and performance indices

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

Planned value PVPV is budgeted cost of scheduled work (BCWS); earned value EVEV is budgeted cost of performed work (BCWP); actual cost ACAC is actual cost of performed work (ACWP). All three use the same scope and status date. EVEV values work at budget rates, not actual expenditure. For an item budget BiB_i and objectively measured completion fraction pip_i, its earned value is piBip_iB_i under proportional earning.

Cumulative planned, earned and actual cost with a common status date; vertical gaps are currency variances.Cumulative planned, earned and actual cost with a common status date; vertical gaps are currency variances.

7.3 Completion forecasts

Choose a forecast based on the reason for the variance. A one-off past expense and a continuing productivity problem need different estimates. Bottom-up re-estimation is appropriate when the remaining work differs substantially from completed work.

Last-minute recall

  • Use a common status date for quantities, dates and costs.
  • Remaining duration depends on remaining quantity and forecast productivity.
  • Actual expenditure is not earned value.
  • CV=EV−ACCV=EV-AC; SV=EV−PVSV=EV-PV; both have currency units.
  • CPI<1CPI<1 means cost inefficiency; SPI<1SPI<1 means less work earned than planned.
  • Smoothing protects finish time; resource levelling may extend it.
  • An old critical path need not remain critical after updating.
  • State the future-performance assumption before choosing an EAC expression.