Chapter 1

Work study and productivity

First establish the method, then measure its work content. A production standard is meaningful only for a stated method, worker performance and allowance basis. Productivity compares output with resources; it is different from output alone.

1.1 Method study

Method study improves how a job is done. Work measurement establishes the time a qualified worker needs at a specified performance level using that method. Select the job, record the facts, examine purpose/place/sequence/person/means, develop and evaluate the improved method, define it, install it, and maintain it. Use ECRS: eliminate, combine, rearrange, simplify.

Recording toolWhat to look for
Operation process chartMain operations and inspections; assembly sequence
Flow process chartOperation ○, inspection □, transport →, delay D-shaped symbol, storage ▽
Flow/string diagramTravel path, distance, crossings and backtracking
Two-handed chartLeft/right hand motions and avoidable waiting
Multiple-activity chartWorker/machine activity and idle time on a common time axis
SIMO chartDetailed simultaneous basic motions, usually from film/video

Motion economy favours short, smooth motions, fixed tool locations, suitable working height, gravity feed where safe, and balanced use of both hands. A combined operation–inspection symbol is a circle within a square. An inspection checks quantity/quality; an operation changes the item or advances its completion.

1.2 Time study and allowances

Work measurement also uses standard data (previously established element times), predetermined motion-time systems (tabulated basic-motion times), and analytical estimation for less repetitive work.

Break a repeatable job into elements. Observe enough representative cycles, identify abnormal observations with reasons, and apply performance rating to worker-controlled time. Do not rate a fixed automatic machine time as if it were manual work.

1.3 Sampling for work measurement

Random observations estimate the fraction of time spent in an activity. Independent, representative observations are essential; taking observations at a repetitive cycle's same phase biases the result. A stopwatch study instead samples element durations.

1.4 Productivity measures

1.5 Learning curves

When the question specifies learning, distinguish cumulative average time from time of the individual unit. The same learning percentage can parameterise either model, but the predictions differ.

Last-minute recall

  • Improve and fix the method before setting its time standard.
  • Multiply observed manual time by the rating factor.
  • An allowance percentage needs a denominator.
  • Work sampling measures time fractions; random timing matters.
  • Round sample size up, not to the nearest integer.
  • Productivity can improve even with unchanged output.
  • Learning percentage is the retained fraction after doubling output.