Lean manufacturing
Lean improves flow while removing work that consumes resources without adding customer value. Small batches require reliable equipment, short setups, capable processes and dependable replenishment. Reducing inventory without addressing its causes can expose stoppages without solving them.
7.1 Waste and improvement methods
| Idea | Meaning for revision |
|---|---|
| Value-stream mapping | Map material/information flow and distinguish processing from waiting |
| Seven wastes | Overproduction, waiting, transport, excess processing, inventory, motion, defects |
| Eighth waste often added | Unused human capability |
| 5S | Sort, set in order, shine, standardise, sustain |
| Kaizen / PDCA | Repeated improvement / plan–do–check–act |
| JIT / pull | Produce needed items when needed; downstream consumption authorises replenishment |
| Jidoka / poka-yoke | Detect abnormality and stop / prevent or expose mistakes |
| SMED | Separate internal setup (machine stopped) from external setup; convert and simplify |
| Heijunka / standard work | Level mix/volume where feasible / define repeatable safe work |
| TPM | Maintain equipment through planned and operator-supported care |
A kanban authorises movement or production; it is not a forecast. Lean and Six Sigma complement each other: flow/waste reduction and variation/defect reduction address different causes of poor performance.
7.2 Flow, takt and work in process
Past papers · ME 2020–2026 (10 papers): 1 question, 2 marks
7.3 Equipment effectiveness
Last-minute recall
- Pull responds to consumption; push releases work from a plan.
- Takt comes from demand; actual cycle time comes from the process.
- Waiting counts in flow time even when it adds no value.
- At fixed throughput, WIP changes in proportion to flow time.
- Kanban counts round up and use the whole replenishment loop.
- OEE multiplies three fractions; do not add them.