Contracts and bidding
A contract allocates scope, payment and risk. Identify who supplies the design, how quantities are measured and how changes are valued before comparing tender prices.
9.1 Payment and delivery forms
| Form | Payment or responsibility basis | Main revision implication |
|---|---|---|
| Lump sum | Agreed price for defined work | Needs clear scope; changes are valued under the agreed variation mechanism |
| Item rate/unit price | Measured accepted quantities times tendered item rates | Final price changes with quantities; BOQ estimates are not guaranteed final quantities |
| Percentage rate | Common quoted percentage above/below a schedule of rates | Apply that percentage to the eligible schedule items |
| Cost plus percentage | Reimbursable allowed cost plus a percentage fee | Fee grows with cost; weak direct incentive to minimise reimbursable cost |
| Cost plus fixed fee | Allowed cost plus agreed fee | Fee does not automatically grow with cost; total payment remains variable |
| Target cost/incentive | Compare actual cost with target, share saving/overrun as agreed | Sharing fractions and any ceilings must be stated |
| Labour-only | Contractor mainly supplies labour | Client usually supplies specified materials; interface responsibility matters |
| Piece work | Agreed rates for defined limited work packages | Do not infer a whole-project obligation from a small work order |
| Design–build/EPC | One contracting entity integrates design and construction; EPC also procures | Delivery responsibility is different from the payment formula |
| Turnkey | Facility delivered ready for the agreed use | Completion/performance requirements must be specified |
| BOT/BOOT and other PPP arrangements | Private role may include finance, operation and eventual transfer | Concession/revenue and lifecycle duties extend beyond construction |
BOT means build–operate–transfer; BOOT adds ownership during the concession. A lump-sum EPC contract combines a payment form with a delivery form; these labels are not mutually exclusive. General classifications do not override the signed contract's provisions.
9.2 Tender evaluation and securities
Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark
In a two-envelope procedure, technical/qualification bids are opened and evaluated first; financial bids are opened for eligible technically responsive bidders according to the tender procedure. This is different from a two-stage process that first develops technical proposals and then invites final bids. Open tendering invites eligible competition; limited tendering restricts invitations; negotiation directly settles terms under the permitted procedure.
The lowest numerical quote is not automatically an award: responsiveness, qualification, evaluated price and the stated selection procedure matter. Bid security/earnest money supports bid obligations; performance security supports performance after award; retention is withheld from payments under the agreed terms. Do not memorise a single percentage or validity period for all contracts.
A variation changes authorised work; escalation adjusts price under an agreed mechanism; an extension of time changes a contractual deadline when justified. Delay damages, defect obligations, dispute resolution and force majeure depend on contract terms. Distinguish the defects-liability period from the construction duration. These are revision definitions, not universal legal entitlements.
9.3 Bid markup and empirical winning probability
Past papers · CE 2020–2026 (14 papers): 1 question, 2 marks
Markup on cost and margin on bid use different denominators (Section 6.5). Past competitor bids can supply an empirical distribution, provided the comparison uses consistent cost estimates and comparable projects. The historical fraction is an estimate, not a guarantee for the next bid.
Last-minute recall
- Lump sum fixes price for defined scope; item rate pays measured quantities.
- Percentage-rate tenders apply a signed percentage to a stated rate schedule.
- Cost-plus fixed fee does not fix the total reimbursed cost.
- Design–build/EPC describes responsibility; lump sum describes payment.
- Technical evaluation precedes eligible financial-bid opening in two-envelope tendering.
- Bid security, performance security and retention have different functions.
- Compare bid/cost ratios on the same basis and handle ties explicitly.
- Expected profit combines margin with probability of winning.