Chapter 9

Contracts and bidding

A contract allocates scope, payment and risk. Identify who supplies the design, how quantities are measured and how changes are valued before comparing tender prices.

9.1 Payment and delivery forms

FormPayment or responsibility basisMain revision implication
Lump sumAgreed price for defined workNeeds clear scope; changes are valued under the agreed variation mechanism
Item rate/unit priceMeasured accepted quantities times tendered item ratesFinal price changes with quantities; BOQ estimates are not guaranteed final quantities
Percentage rateCommon quoted percentage above/below a schedule of ratesApply that percentage to the eligible schedule items
Cost plus percentageReimbursable allowed cost plus a percentage feeFee grows with cost; weak direct incentive to minimise reimbursable cost
Cost plus fixed feeAllowed cost plus agreed feeFee does not automatically grow with cost; total payment remains variable
Target cost/incentiveCompare actual cost with target, share saving/overrun as agreedSharing fractions and any ceilings must be stated
Labour-onlyContractor mainly supplies labourClient usually supplies specified materials; interface responsibility matters
Piece workAgreed rates for defined limited work packagesDo not infer a whole-project obligation from a small work order
Design–build/EPCOne contracting entity integrates design and construction; EPC also procuresDelivery responsibility is different from the payment formula
TurnkeyFacility delivered ready for the agreed useCompletion/performance requirements must be specified
BOT/BOOT and other PPP arrangementsPrivate role may include finance, operation and eventual transferConcession/revenue and lifecycle duties extend beyond construction

BOT means build–operate–transfer; BOOT adds ownership during the concession. A lump-sum EPC contract combines a payment form with a delivery form; these labels are not mutually exclusive. General classifications do not override the signed contract's provisions.

9.2 Tender evaluation and securities

Past papers · CE 2020–2026 (14 papers): 1 question, 1 mark

In a two-envelope procedure, technical/qualification bids are opened and evaluated first; financial bids are opened for eligible technically responsive bidders according to the tender procedure. This is different from a two-stage process that first develops technical proposals and then invites final bids. Open tendering invites eligible competition; limited tendering restricts invitations; negotiation directly settles terms under the permitted procedure.

The lowest numerical quote is not automatically an award: responsiveness, qualification, evaluated price and the stated selection procedure matter. Bid security/earnest money supports bid obligations; performance security supports performance after award; retention is withheld from payments under the agreed terms. Do not memorise a single percentage or validity period for all contracts.

A variation changes authorised work; escalation adjusts price under an agreed mechanism; an extension of time changes a contractual deadline when justified. Delay damages, defect obligations, dispute resolution and force majeure depend on contract terms. Distinguish the defects-liability period from the construction duration. These are revision definitions, not universal legal entitlements.

9.3 Bid markup and empirical winning probability

Past papers · CE 2020–2026 (14 papers): 1 question, 2 marks

Markup on cost and margin on bid use different denominators (Section 6.5). Past competitor bids can supply an empirical distribution, provided the comparison uses consistent cost estimates and comparable projects. The historical fraction is an estimate, not a guarantee for the next bid.

Last-minute recall

  • Lump sum fixes price for defined scope; item rate pays measured quantities.
  • Percentage-rate tenders apply a signed percentage to a stated rate schedule.
  • Cost-plus fixed fee does not fix the total reimbursed cost.
  • Design–build/EPC describes responsibility; lump sum describes payment.
  • Technical evaluation precedes eligible financial-bid opening in two-envelope tendering.
  • Bid security, performance security and retention have different functions.
  • Compare bid/cost ratios on the same basis and handle ties explicitly.
  • Expected profit combines margin with probability of winning.