| Activity, event and deadline times | ta,tij,Ei,Li,Tproj,Td | s, h, day or week | One time basis per calculation; events instantaneous; Td=Tproj in ordinary CPM. |
| Activity early/late starts and finishes | ES,EF,LS,LF | time | Subscripts identify activity. |
| Event slack and activity floats | Si,TF,FF,IF,Fint | time | Independent float clipped at zero; interfering float is total minus free. |
| Precedence sets, starts and lag | P(a),S(a),sa,ℓab | sets; time | Positive lag is minimum separation; negative lag is a lead. |
| PERT estimates and random duration | to,tm,tp,te,Ta,Tπ | time | Optimistic, modal, pessimistic, estimated mean; random activity/path times. |
| Path and service statistics | mπ,sπ,σa,σa2,Cov,mS,σS2 | time; time squared for variance/covariance | Statistical sigma, not stress; mS=E[S] for service time. |
| PERT network estimate and normal scores | TPERT,Φ,zd,zp,p,T1,T2 | time; dimensionless probabilities/scores | Φ standard-normal CDF, zp=Φ−1(p). |
| Normal/crash durations and reduction | tn,a,tc,a,ya | time | 0≤ya≤tn,a−tc,a. |
| Direct and total costs | Cn,a,Cc,a,Ca,Ctotal,C0,ΔCdirect,ΔCtotal | ₹ | Project costs, not rates. |
| Crash slope, overhead and saved duration | ka,h,ΔTsaved | ₹/time; time | Saved duration positive for a reduction. |
| LP decisions and objective | xj,xj+,xj−,vj,Z,Z0,Z∗ | decision units; objective units | LP variables continuous unless stated; vj is a bound-shift variable only in Section 4.3. |
| LP coefficients and limits | A,aij,bi,cj,ℓj,Δb | resource/decision; resource; objective/decision; decision | Each constraint has homogeneous resource units. |
| Slack/surplus and dual value | si,yi,ΔZ∗ | resource; objective/resource; objective | Dual signs depend on primal direction. |
| Simplex basis and dictionary | B,N,xB,xN,cB,cN,bˉ,AˉN,aˉiq | entry-dependent | N is nonbasic matrix here, not queue occupancy. |
| Reduced costs and pivot quantities | rj,zj,θ,Ri,p,q | objective/decision; decision; row; indices | rj=cj−zj; p leaving row, q entering column. |
| Artificial variables and penalty | aiart,w,M | scaled row units; penalty supplies objective units | Phase-I w is artificial sum; M symbolic positive penalty. |
| Transportation/assignment quantities | xij,si,dj,cij,ui,vj,Δij,θ,αi,βj,K,h | shipment; unit cost; cost/time in assignment | ui,vj MODI potentials; αi,βj shifts; K transformation constant and h Hungarian uncovered minimum locally. |
| Flow graph, supply and arc quantities | A,V,bi,xij,uij,ℓij,cij,Z | sets; quantity or rate; currency/quantity; currency or currency/time | Positive node supply is outflow minus inflow. |
| Shortest-path quantities | wij,dj,s,t | distance, time or cost; node labels | s,t are source/sink labels here. |
| Max-flow residuals and cuts | F,F∗,re,rij,δ,P,S | flow units; path/node sets | P residual path; S source-side node set, distinct from probability and service time. |
| Queue rates and counts | λ,λeff,λn,λf,μ,μn,c,K,N,Nt,Nq | jobs/time; counts | μ per-server rate; K includes service; N population size or random system count as locally specified. |
| Arrival, service and waiting times | A,S,Tq,Ts,t | time | Random interarrival, service, queue and total times; A is not an LP matrix here. |
| Queue averages | L,Lq,W,Wq | jobs; time | Subscript q excludes service; W is a mean, not random time. |
| Queue probabilities and load | pn,p0,ρ,a,Pwait | dimensionless | a=λ/μ; ρ=λ/(cμ) for c servers, or λ/μ for one. |
| Queue cost parameters | hq,Cs | ₹/(job-time); ₹/(server-time) | Use queue or system count according to costing boundary. |
| Generic dimensions and indices | m,n,i,j,k,π | counts/indices | Meaning local to each model; π a path in PERT or an assignment permutation in checks. |