Propagation delay and clock timing

A correct truth table does not guarantee correct operation at a chosen clock rate. Separate maximum-delay constraints, which protect setup, from minimum-delay constraints, which protect hold. Use the stated gate-delay model when tracing waveforms.

6.1 Arrival times and critical paths

Past papers · CS 2014–2026 (23 papers): 1 question, 2 marks · EC 2020–2026 (7 papers): 2 questions, 3 marks

Propagation delay tpdt_{pd} bounds the time until an output settles after a valid input change. Contamination delay tcdt_{cd} bounds the earliest possible output change. Rise and fall delays can differ. A critical path is the longest relevant input-to-output or register-to-register path; do not add delays of parallel paths.

For a full adder built from two XOR/AND half adders and one OR, write P=A⊕BP=A\oplus B, S=P⊕CinS=P\oplus C_{\mathrm{in}}, Cout=AB+PCinC_{\mathrm{out}}=AB+PC_{\mathrm{in}}. With XOR delay tXt_X, AND delay tAt_A and OR delay tOt_O, an arrival recurrence is more reliable than multiplying a single “full-adder delay” by the number of bits: aP=max⁡(aA,aB)+tXa_P=\max(a_A,a_B)+t_X, aS=max⁡(aP,aC)+tXa_S=\max(a_P,a_C)+t_X, and aC+=max⁡(max⁡(aA,aB)+tA,max⁡(aP,aC)+tA)+tOa_{C^+}=\max(\max(a_A,a_B)+t_A,\max(a_P,a_C)+t_A)+t_O.

6.2 Setup, hold and clock skew

Past papers · EC 2020–2026 (7 papers): 2 questions, 4 marks

Setup time tsut_{su} is the required stable-data interval before a capture edge; hold time tht_h is the interval after it. Clock-to-Q has a maximum tcq,max⁡t_{cq,\max} and minimum tcq,min⁡t_{cq,\min}. Define skew sk=tcapture clock−tlaunch clocks_k=t_{\mathrm{capture\ clock}}-t_{\mathrm{launch\ clock}}: positive means the capture clock arrives later.

Launch-to-capture timing with explicitly positive capture skew.Launch-to-capture timing with explicitly positive capture skew.

For opposite-edge launch/capture, replace the full-period separation with the actual edge separation, often Tclk/2T_{\mathrm{clk}}/2 only for a 50% duty clock. Reset release has recovery/removal requirements analogous to setup/hold. Latches can borrow time while transparent; do not apply an edge-triggered full-cycle formula blindly to a latch pair.

6.3 Delayed events, latency and throughput

Past papers · EC 2020–2026 (7 papers): 2 questions, 3 marks

For a circuit with feedback and specified delays, maintain an event list: clock times, scheduled gate-output changes, and asynchronous control changes. At each active edge sample the input value actually present immediately before that edge, then schedule the flip-flop output after its clock-to-Q delay. Do not replace a delayed feedback signal by an instantaneous next-state expression.

If a question gives an ideal transport delay, every transition is shifted by that delay. An inertial gate can reject pulses shorter than its specified rejection interval. When neither model nor setup/hold is supplied, use the ideal model the question explicitly requests; do not infer reliable hardware behaviour from it. If an input transition exactly coincides with sampling without a defined ordering, flag the ambiguity.

If data first enters register 1 at an edge, it reaches register LL after L−1L-1 additional edges. Specify the starting event before counting cycles. A chain can have several-cycle latency while still producing a new output every cycle after filling.

6.4 Ripple settling and feedback oscillation

Past papers · EC 2020–2026 (7 papers): 1 question, 2 marks · EE 2020–2026 (7 papers): 1 question, 1 mark

A loop that inverts once per traversal has no stable binary fixed point in the ideal delay model; a non-inverting feedback loop can retain a stable state. Oscillation frequency depends on actual propagation delays and loading. A MUX fed by its complemented output behaves as an odd-inversion loop only when that feedback input is selected. A free-running ring oscillator is different from a clocked ring counter.

Last-minute recall

  • Latest arrival uses maximum path delay; earliest change uses minimum.
  • Parallel gate delays do not add.
  • Compute sum and carry endpoints separately in an adder.
  • Positive capture skew helps setup and hurts hold under this definition.
  • Hold failure cannot normally be repaired by lengthening the period.
  • Timing violations make sampled data uncertain.
  • Count latency from a stated launch event.
  • One full oscillation traverses both rising and falling transitions.